Who received federal funding for EV charging stations?

The federal Zero Emission Vehicle Infrastructure Program (ZEVIP) had 386 public Funding Intelligence disclosures dated January 2023 to July 2026. The median positive amount was $287,500. The examples range from a $100,000 apartment charging project to a $3 million public charging project. The funding per charger depends on what is being built, where it will be installed and which costs the agreement covers. Natural Resources Canada’s description of ZEVIP
How much EV charging funding was disclosed?
Of 376 records with a positive amount, 94 reached $1 million. That is exactly one in four. The middle half ranged from $129,477 to $992,500, which shows how far a single median can be from either end of the distribution. For a building owner or operator, the useful comparison is another project with a similar site and charging setup.
376 records with a positive amount.
Which provinces had the most ZEVIP disclosures?
Ontario accounted for 191 of the 386 records, followed by British Columbia (84), Québec (46) and Alberta (31). Compare the share of disclosures rather than assuming the same share of chargers. A recipient can be listed in one province while an agreement covers installation across several provinces.
386 records in this extract.
What kinds of EV charging projects received funding?
An October 2025 federal backgrounder gives a set of projects with both the announced support and the planned installation. The projects serve different users, which helps explain why dividing by the number of chargers is only a starting point. Federal backgrounder on Atlantic charging projects
Scroll horizontally to see all columns.
Announced recipient | Charging location and planned installation | Announced funding |
|---|---|---|
Southwest Properties | Apartment buildings, 20 Level 2 chargers | $100,000 |
Nikmaq Trading | Near Halifax International Airport, 10 Level 3 chargers | $742,500 |
Steele Auto Group | Dealerships, 37 Level 2 and 28 Level 3 chargers | $1.3 million |
Nova Scotia Power | Public locations, 60 Level 3 chargers | $3 million |
Level 2 chargers are useful where vehicles can stay plugged in longer, such as apartment parking. Shorter visits can require a different installation. Compare the electrical work, utility connection, number of sites, network operating costs and expected use before applying an announced per-charger ratio to your project.
How should you budget a charger installation?
Identify the drivers who will use it and how long they typically park.
Record existing electrical capacity, the power required by the proposed equipment, and any utility or construction work.
Ask vendors to separate the equipment, installation, commissioning and recurring fees.
Add an occupancy or usage forecast and show how the project works if demand builds gradually.
Questions about EV charging station funding
Can an apartment building use public charging projects as a benchmark?
Compare with an installation that serves similar users. An apartment project usually needs estimates for parking access, load management and overnight use. A public fast-charging site can have very different power and operating requirements. The $100,000 Southwest Properties announcement is a more relevant example to investigate than a mixed network of Level 2 and Level 3 units.
Are disclosed amounts the same as cost per charger?
They are the support recorded or announced under the agreement. To calculate installed cost per charger, you also need total eligible and ineligible project costs, a definition of the units counted and details of any electrical or civil work. Those inputs are often missing from a public announcement.
Data coverage and methodology
Funding Intelligence draws on the federal grants and contributions disclosures. The extract covers 386 records dated January 11, 2023 through July 29, 2026. Amount statistics use 376 records with positive values in Canadian dollars. The year groups use the dates recorded by the source.
Scroll horizontally to see all columns.
Recorded year | Records | Positive amounts | Median positive amount |
|---|---|---|---|
2023 | 125 | 125 | $305,000 |
2024 | 28 | 28 | $618,716 |
2025 | 213 | 203 | $250,000 |
2026 | 20 | 20 | $662,877 |
Scroll horizontally to see all columns.
25th percentile | Median | 75th percentile |
|---|---|---|
$129,477 | $287,500 | $992,500 |
Scroll horizontally to see all columns.
Reported location | Records | Median positive amount |
|---|---|---|
Ontario | 191 | $234,908 |
British Columbia | 84 | $387,121 |
Québec | 46 | $190,000 |
Alberta | 31 | $270,000 |
Nova Scotia | 8 | $861,250 |
Manitoba | 7 | $570,000 |
New Brunswick | 6 | $600,000 |
Saskatchewan | 5 | $1,905,000 |
Historical disclosures can contain amendments or multiple agreements for the same recipient. The unit of analysis is the disclosure record. The location table lists areas with at least five records.