How to prepare a commercial Atlantic Fisheries Fund proposal

A commercial Atlantic Fisheries Fund proposal should connect an operational problem to a measurable result and show how you will pay for the work. Use this example to prepare a proposal for a seafood processing or aquaculture investment and match each part of your file to Fisheries and Oceans Canada (DFO) guidance.
Choose the pillar and proposal guide
The Atlantic Fisheries Fund supports eligible projects in Nova Scotia, New Brunswick, Prince Edward Island, and Newfoundland and Labrador. Installing proven equipment to improve a processing line may fit Infrastructure. Developing or commercializing a new process or technology may fit Innovation. Describe the work you will actually do and ask DFO which pillar applies and whether intake is available for it.
Choose the guide by the assistance requested from the Fund. DFO provides a non-repayable guide for requests below $100,000 and a repayable guide for requests above $100,000. At exactly $100,000, ask DFO which guide to use. The example below uses the under-$100,000 guide to illustrate a file. DFO determines eligibility and contribution terms.
Fictional project brief: a whitefish packaging line
A seafood processor in southwestern Nova Scotia weighs trays by hand and pulls finished packages off the line for rework. Four weeks of sample production logs show 300 trays per hour and 5% weight-related rework. The proposed project installs an in-line checkweigher and trains operators to handle exceptions and record results.
Applicant and site: an incorporated processor with an existing Nova Scotia plant. Its operations manager leads installation and its quality supervisor tracks results.
Work plan: confirm the layout and quote in month one, receive and install the unit in months two and three, and validate accuracy and train operators in month four. The schedule assumes DFO confirms when the applicant can commit costs.
Targets: reach 360 trays per hour and reduce weight-related rework to 2%. Compare four weeks of post-installation logs on equivalent products and shifts with the baseline. Assign calibration and maintenance to the plant team.
Cost and procurement: $86,000 for the checkweigher, $28,000 for integration, $16,000 for commissioning, and $10,000 for training, for a project cost of $140,000 before GST/HST. Quote each item separately. Document which Canadian and Indigenous suppliers were considered where feasible and why the proposed supplier meets the line and service needs.
Risks and controls: schedule installation during planned downtime and keep the existing manual checks as a fallback until the quality supervisor signs off.
Funding sources for the fictional project
Scroll horizontally to see all columns.
Funding source | Amount | Status and proposed use |
|---|---|---|
Applicant cash | $55,000 | Confirmed in the example. $21,000 for equipment, $16,000 for commissioning, $10,000 for training, and $8,000 for integration. |
Bank term loan | $20,000 | Application pending. Proposed for the remaining integration costs. |
Atlantic Fisheries Fund | $65,000 | Requested in the example. Proposed for part of the equipment cost. |
Total funding if all sources come through | $140,000 | $55,000 confirmed, with $85,000 still pending or requested. |
The proposed request is $65,000 against a $140,000 project. The allocations illustrate a balanced budget and still need an eligibility review. If the loan is declined, the processor needs another source or a revised plan. Use written confirmation for secured amounts and disclose other funding and any amounts owed to governments as required by the guide.
Match each document to the proposal
Scroll horizontally to see all columns.
Section in the DFO guide | Evidence to prepare |
|---|---|
Application form and applicant details | Complete the current financial assistance form with the legal name, contact, project lead, location, and any partners. |
Project summary, objectives and details | Attach the baseline logs, equipment specs, schedule, test plan and target metrics. Explain the operational benefit and how your team will measure and sustain it. |
Business plan, risk and organizational capacity | Show projected savings, downtime assumptions, installation risks and who owns delivery. Identify the roles of the supplier and plant team. |
Financial details and supporting documents | Include the budget, funding sources and status, current and prior two years of financial statements for the incorporated applicant, relevant itemized quotes, technical specs, and required licence or permit evidence. |
Before committing costs or submitting
Review the current application form and submission instructions. The proposal guidelines say to apply before making financial or legal project commitments. Bring your pillar, requested amount and quotes to the DFO program team at 1-844-795-9718 to confirm intake, the applicable guide and a secure way to submit financial records.